The Seven Dwarfs: Often Ignored
Highway Project Issues
The highway planning process
includes following all applicable laws and regulations. Over the last few
years, over $200 million of highway projects crossing National Forest System
lands on the Tonto National Forest in Arizona has given Terry J. Brennan,
Highway Program Leader, lots of experience. He has identified seven major
issues in highway projects that are frequently left out of the planning
process. These issues may not be anticipated as part of the construction
project and often impact areas well outside the right-of-way.
Brennan calls these issues the
‘Seven Dwarfs’ of highway project planning. While these ‘Seven
Dwarfs’ need to be adequately analyzed, cleared, documented and mitigated,
they are often forgotten until too late in the process to avoid delays,
resource impacts, and non-compliance with laws and regulations
Several of these issues require
separate clearances and documents in addition to the NEPA process prepared
for the primary project. Awareness of the possibility that these issues
may come up should help USDA Forest Service resource specialists to plan
for a timely resolution to the potential impacts. Others outside of the
USDA Forest Service may find this information useful as well, since the
‘Seven Dwarfs’ are not limited to projects on National Forest
System lands.
Brennan’s ‘Seven
Dwarfs’
1. Borrow and Waste Sites/Material
Balance
High speed highway projects are
typically not light on the land, and require large cuts and fills to provide
the configuration needed for high speed lanes. These cuts and fills create
a need for material balance. The tremendous volume of material requires
a place for temporary or permanent storage. Borrow and waste sites may be
needed to complete these material balance requirements, and need to be analyzed
in the NEPA document.
2. Contractor’s Staging
Areas
Large earth-moving equipment
is needed during construction, often in large numbers. Contractors need
large areas of relatively flat ground to stage these expensive vehicles
safely. Many other supplies and materials require large areas as well. These
include office trailers, culverts, gravel and aggregate, and other construction
materials. These staging areas need to be chosen and analyzed with care,
and have appropriate clearances.
3. Water for Construction
Large construction projects can
consume tremendous quantities of water, using up to a million gallons each
day. Surface water can be readily depleted at that rate, with serious consequences
on aquatic resources particularly in arid regions. Construction water sites
require careful analysis, with maximum withdrawal limits as appropriate.
Consider seasons of use in determining maximum withdrawal limits, since
avoiding spawning or breeding seasons for fish and wildlife are important
seasonal considerations.
4. Access for Construction and
Geotechnical Investigation
Crews associated with the highway
project may need to access the location of a future highway or realignment
over a far different route than the future highway. These access needs may
be well outside the right-of-way limits. Geotechnical investigations can
require roads capable of supporting large drilling equipment or other large
vehicles.
A need to detour traffic around
construction sites may affect areas that are not clearly delineated in the
NEPA document. These sites may affect considerable acreage if the speed
of the traffic is not reduced or if the construction is major.
Anticipate and analyze access
management needs as part of the NEPA document, and determine mitigation
for access routes no longer needed after construction is complete.
Access routes can open up previously
unroaded areas, so barriers during construction or geotechnical investigations
might be necessary to prevent establishment of public use. Access for projects
through sensitive wildlife areas such as nesting territories or winter range
may need seasonal restrictions. Consideration early in the planning process
may avoid construction delays.
5. Utilities
Utilities are frequently collocated
with highways, so when highways are reconstructed or realigned, the need
to consider new locations for utilities becomes important. Utilities are
often outside the right-of-way, so the analysis of the effect of a highway
project on their location is often omitted from NEPA analysis. New highway
alignments may necessitate new utility locations, and different utilities
(power, telephone, cable, water lines) may need different routings.
Forest Service planners need
to consider numerous aspects of these changes, including some or all of
the following. Clearances may need to be obtained for pole placement or
replacement. Sometimes highways are closed due to realignment but the utilities
remain in place, so it must be determined whose responsibility it is to
maintain the road and to what standard, particularly if the road closure
is considered mitigation for the impacts of the construction. The type of
road access restriction needs to be considered and agreed to by all parties,
including all utilities, prior to the issuance of final clearances. An opportunity
may arise to consider underground utilities at the time of reconstruction.
6. Mitigation Projects
Mitigation for highway project
impacts also need NEPA consideration and appropriate clearances obtained.
Mitigation projects may be well outside the right-of-way. It is important
to determine and document who is responsible for planning, funding and implementation
of mitigation projects, particularly if they are long-term projects and
may involve a change of personnel. Since this is often an interagency agreement,
a memorandum of understanding or agreement is recommended to avoid future
misunderstandings. This memorandum could be used to document who would do
the necessary environmental analysis and who will fund it if mitigation
is not included in the highway project NEPA document.
Strongly consider monitoring
in all highway projects; monitoring falls under the same funding and implementation
concerns as mitigation. Monitoring is typically complex, so development
of a plan prior to the issuance of a Letter of Consent ensures that it is
clear who is responsible, and how the information will be collected and
used.
7. Impact of Outside Agencies
and Direction
The Forest Service is subject
to many regulations and other direction that have major impacts on the completion
of a highway project crossing National Forest System lands. These include
such regulations as 4F, 401, 404, SWPP, Clean Water Act, US Fish and Wildlife
Service consultation requirements, SHPPO, and other mitigation or local
issues. Brennan notes that ‘the quickest way to get a ranger in jail
is to violate the Clean Water Act,’ so it is important that all of
these other regulations and requirements are met as well as internal policy
requirements. Failure to plan for and obtain permits and clearances in a
timely fashion will delay projects, and may lead to major resource damage
as well.
State and federal highway projects
function with a somewhat different interpretation of NEPA requirements,
FWS consultation agreements, and other constraints, particularly because
of the rapid planning and implementation schedule of most highway projects.
Outside contractors are typically used for highway project planning, sometimes
with minimal use of local Forest Service resource specialist knowledge.
It is the Forest Service’s
responsibility to ensure all its applicable laws, regulations and policies
are followed, and contractors may not be aware of all necessary procedures.
The 1998 Memorandum of Understanding between the USDA Forest Service and
the Federal Highway Administration directs the Forest Service, acting as
an agent of the FHWA, to be responsible for monitoring and enforcement of
all applicable environmental legislation for highways on NFS lands (Section
I), tied to the issuance of the Letter of Consent to allow a highway as
a reasonable use of NFS lands.
Sandra Jacobson, USDA Forest Service, August 4, 2002